activities that miss the planned start

Member for

18 years 2 months

Ha Ha, another famous P3 trick.



The problem is that you can’t filter by baseline date



What you CAN do is set up 2 custom data items in your "live" plan;



PLST Planned start

PLFN Planned Finish



These may already be set up, they are part of one of the standard templates.



You then run a global change (after backing up - sorry if I said this before, but GCh can be so dangerous) which sets these custom data items to the ES and EF of the corresponding activities in your baseline. You may find this GCh under GL04 - Store Planned Dates for All Activities as it is also contained in one of the templates, designed specifically to solve your problem.



Now you can filter on your baseline dates by setting the filter against the custom data items.



then, to see activities which should have started but have not...



PLST-LT-DD+0H

(Planned Start < Data Date)

AND

AS-EQ-BLANK

(Actual start = " ")



Hope this helps