You can format the bar of particular activities to change colour and or pattern by selecting the activities then format > selected bars> modify bar format.
Hope this helps.
Karen
Member for
19 years 7 months
Member for19 years7 months
Submitted by Karim Mounir on Mon, 2007-09-24 03:28
1- U should have a cloud bitmap because P3 doesnt have any, if u have MS Word then u can find one from the Clip Art (click on Insert-->Clip art and search with keyword: Cloud).
2- Once u got the bitmap from MS Word, copy/paste it in Paint and save it as .bmp (Monochrome Bitmap).
3- Open the schedule in which u want to add the cloud, click on "Insert"-->"Object", 2 windows appear cancel the one titled "Insert Object".
4- Now in the other window (titled "Tools"), click on button showing Triangle, Circle & square (it is used for inserting objects like bitmaps and text).
5- Once pressed, click anywhere in the Gantt Chart area, a window titled "Primavera Symbol Selection" appears, change the "List of File Types" to "Bitmap Files .bmp" and browse to the cloud.bmp which u have saved earlier.
6- Once selected, it appears in the Gantt Chart, resize it and move to define the activities u want.
Member for
21 years 5 monthsRE: Hightlight some activities.
To cloud out between two dates for the entire programme:
Form the menu choose View; Attachment Tools.
Click on the bottom right tool (two verticals with a squiggle across them).
Click in the bar area and drag to the right.
You now have a shaded area and the dates can be adjusted with the handles mid way down the screen.
Hope this helps.
Member for
18 years 5 monthsRE: Hightlight some activities.
Hi Sundar,
You can format the bar of particular activities to change colour and or pattern by selecting the activities then format > selected bars> modify bar format.
Hope this helps.
Karen
Member for
19 years 7 monthsRE: Hightlight some activities.
Hi Sundar,
For question #2:
1- U should have a cloud bitmap because P3 doesnt have any, if u have MS Word then u can find one from the Clip Art (click on Insert-->Clip art and search with keyword: Cloud).
2- Once u got the bitmap from MS Word, copy/paste it in Paint and save it as .bmp (Monochrome Bitmap).
3- Open the schedule in which u want to add the cloud, click on "Insert"-->"Object", 2 windows appear cancel the one titled "Insert Object".
4- Now in the other window (titled "Tools"), click on button showing Triangle, Circle & square (it is used for inserting objects like bitmaps and text).
5- Once pressed, click anywhere in the Gantt Chart area, a window titled "Primavera Symbol Selection" appears, change the "List of File Types" to "Bitmap Files .bmp" and browse to the cloud.bmp which u have saved earlier.
6- Once selected, it appears in the Gantt Chart, resize it and move to define the activities u want.
Thats all!
Regards,
Karim