Calendars in P3

Member for

22 years 5 months

Good question, it’s a programme of major machinery overhauls, gas turbines and compressors, which spans 10 months. Each machine overhaul works 24 hours round the clock. Agree that it is normally only shutdowns planned in hours taking a few weeks at the most.

Member for

22 years 5 months

Hi John,



Might be a silly question, but if your schedule is a year, why are you doing it in hours?



I have done shutdowns in hours, but mostly all in days.



Kevin