Primavera Project Planner - P3 Member for 20 years 2 months Member for 20 years 2 months Submitted by John Hartman on Mon, 2007-08-20 11:39 Permalink RE: Cost Loading Report / Profile not including actuals I resolved my problem. I found that the reporting periods were not in aligned (schedule and cost data). Once I aligned, the cost per period matched up. Log in or register to post comments
Member for 20 years 2 months Member for 20 years 2 months Submitted by John Hartman on Mon, 2007-08-20 11:39 Permalink RE: Cost Loading Report / Profile not including actuals I resolved my problem. I found that the reporting periods were not in aligned (schedule and cost data). Once I aligned, the cost per period matched up.
Member for
20 years 2 monthsRE: Cost Loading Report / Profile not including actuals
I resolved my problem. I found that the reporting periods were not in aligned (schedule and cost data). Once I aligned, the cost per period matched up.