Primavera Project Planner - P3 Member for 24 years 6 months Member for 24 years 7 months Submitted by Paul Harris on Mon, 2007-08-13 10:50 Permalink RE: leveling type The activity type needs to be independent and resources driving before this option will work. Paul E Harris Eastwood Harris Pty Ltd, Melbourne, Australia Planning and Scheduling Training Manual & Book Publishers & Consulting www.eh.com.au Log in or register to post comments
Member for 24 years 6 months Member for 24 years 7 months Submitted by Paul Harris on Mon, 2007-08-13 10:50 Permalink RE: leveling type The activity type needs to be independent and resources driving before this option will work. Paul E Harris Eastwood Harris Pty Ltd, Melbourne, Australia Planning and Scheduling Training Manual & Book Publishers & Consulting www.eh.com.au
Member for
24 years 6 monthsRE: leveling type
The activity type needs to be independent and resources driving before this option will work.
Paul E Harris
Eastwood Harris Pty Ltd, Melbourne, Australia
Planning and Scheduling Training Manual & Book Publishers & Consulting
www.eh.com.au