Duration with decimal point...

Member for

23 years

Hi Rick,

The calculation in P3 works in whole units - your only option for parts of a day is hours, but you can run a secondary schedule, for example a steel erection schedule, and import or key in a summary level into your main schedule. Even if your client demands it as backup it will only detail one part of your work.

Member for

18 years 9 months

Hi Rick



No you can’t! I agree to Raviraj, without decimals should be ok for longer projects. In P3e it would be poosible but there too I didn’t use it - for longer projects.



Dieter

Member for

20 years 7 months

Hi Rav and Anoon,



Thanks for your immediate response, but is there a possibility that i could set up my duration with a decimal point? like 2.3 days, 2.4 days, etc, etc. because when i enter the duration with decimal point the primavera will round it off to a whole number, and when you organized it to see the schedule duration it is less of what i have planned.is there a possibility for p3 to accept whatever duration i encoded.

Thanks Again.

Member for

18 years 5 months

Hi Rick,



If the project is long, why u want to put duration in hours. Do u want to be so transparent with ur client that u will activity worth in hours only.



Even, it is neither required by Client/Consultant nor by project team.



Hours are used in mostly maintenance projects, where shutdown means loosing money.



Its of no point in putting duartion in hours for a long project



Cheers,



Raviraj

Member for

19 years 1 month

i suggest that you should never do that, if it’s day or hour so be it!