That depends on how you want to see the total percent complete , if u want to see in all the levels , then u have to select top in all the levels , if you want to see the total complete of the project then u have to select "top" only in the topmost level.
I am working on Pranab option to get a percent complete report for the project .when I go to organize in group by column I have Level 1, Level 2 and level 3.
Please let me know that in Total column do I have to select “Top” for all three levels(Level 1, Level 2 and Level 3)
Thanks
Member for
22 years 9 months
Member for22 years9 months
Submitted by Alexandre Faul… on Tue, 2007-07-31 04:43
Ravi has answer your question in some sort, im in doubt if it meets your needs.
You need to present your report to expect the audience to undestand.
first,make a baseline in p3 as target, then decide what algorithm to compute % complete, is it physical, unit, or duration, allocate either MH or cost. the go to menu.. report > cost/resources,then print
Member for
19 years 1 monthRE: Project Percent complete
make sure that you understand how your Percent Complete was reckoned
Member for
18 years 9 monthsRE: Project Percent complete
Hello Zameer ,
That depends on how you want to see the total percent complete , if u want to see in all the levels , then u have to select top in all the levels , if you want to see the total complete of the project then u have to select "top" only in the topmost level.
HTH
Deb
Member for
18 years 5 monthsRE: Project Percent complete
Thanks for your help guys.
I am working on Pranab option to get a percent complete report for the project .when I go to organize in group by column I have Level 1, Level 2 and level 3.
Please let me know that in Total column do I have to select “Top” for all three levels(Level 1, Level 2 and Level 3)
Thanks
Member for
22 years 9 monthsRE: Project Percent complete
Zameer,
you should 1st create a wbs structure where Level 1 is the whole project,
then organize the layout to show the workbreakdown, and display the total for the 1st level
Alexandre
Member for
18 years 9 monthsRE: Project Percent complete
hello zameer,
Use format>organize>work break down , and then select Top in total , u should be getting the subtotal at the highest wbs level for percent complete ,
regards
deb
Member for
20 years 2 monthsRE: Project Percent complete
Ravi has answer your question in some sort, im in doubt if it meets your needs.
You need to present your report to expect the audience to undestand.
first,make a baseline in p3 as target, then decide what algorithm to compute % complete, is it physical, unit, or duration, allocate either MH or cost. the go to menu.. report > cost/resources,then print
i hope it helps
regards.
Member for
18 years 5 monthsRE: Project Percent complete
For the overall project - percent complete, take the LEVEL 1 print-out. Its a part of monthly report submission in most of the orgzs.
In the percent complete column, it will show % complete.
In the footer, (If the finish date is not imposed) it will show the updated completion date.
Cheers,