Problems coverting Microsoft Project schedule to P3

Member for

24 years 6 months

There is a technical article on my web site that may assist you.



The two products do calculate differently and it is often very hard to get them to calculate the same. This is explained in my article.



Paul E Harris

Eastwood Harris Pty Ltd, Melbourne, Australia

Planning and Scheduling Training Manual & Book Publishers & Consulting

www.eh.com.au

Member for

20 years 3 months

To David Andreotti



Hello David



as I wrote a macro in Excel for converting I’m very interested in your function as well. Could you send it to me, maybe I could send you some new ideas or could take over some of your thoughts.



Hannes

Member for

18 years 9 months

Swapna,



MPX format reflects a status of scheduling about 20 years ago. I suppose, you used some features in MSP which are not covered by MPX.

If you have P3e/P5 as well. there is a much simpler way: You switch-off "resource-driven" and switch on "ignore resource calendar" in MSP --> import MPP into P3e ---> schedule and check dates (mostly the MSP-calendar was not maintained) --> Export to P3.



Regards



Dieter