as I wrote a macro in Excel for converting Im very interested in your function as well. Could you send it to me, maybe I could send you some new ideas or could take over some of your thoughts.
Hannes
Member for
18 years 4 months
Member for18 years4 months
Submitted by Swapna Boinpally on Sun, 2007-07-29 14:17
MPX format reflects a status of scheduling about 20 years ago. I suppose, you used some features in MSP which are not covered by MPX.
If you have P3e/P5 as well. there is a much simpler way: You switch-off "resource-driven" and switch on "ignore resource calendar" in MSP --> import MPP into P3e ---> schedule and check dates (mostly the MSP-calendar was not maintained) --> Export to P3.
Member for
24 years 6 monthsRE: Problems coverting Microsoft Project schedule to P3
There is a technical article on my web site that may assist you.
The two products do calculate differently and it is often very hard to get them to calculate the same. This is explained in my article.
Paul E Harris
Eastwood Harris Pty Ltd, Melbourne, Australia
Planning and Scheduling Training Manual & Book Publishers & Consulting
www.eh.com.au
Member for
20 years 3 monthsRE: Problems coverting Microsoft Project schedule to P3
Same request as before to David Andreotti but now with e-mail address : Hannes.de-Bruyne@Hochtief.de
Member for
18 years 9 monthsRE: Problems coverting Microsoft Project schedule to P3
Dear Sir,
Please send me a copy as well, to deb.icd@tajnet.com
regards
deb
Member for
20 years 3 monthsRE: Problems coverting Microsoft Project schedule to P3
To David Andreotti
Hello David
as I wrote a macro in Excel for converting Im very interested in your function as well. Could you send it to me, maybe I could send you some new ideas or could take over some of your thoughts.
Hannes
Member for
18 years 4 monthsRE: Problems coverting Microsoft Project schedule to P3
P.S. If am not wrong you can just click on the mail icon next to member names to send private e-mail messages.
Member for
18 years 5 monthsRE: Problems coverting Microsoft Project schedule to P3
For me too David,
ravirajab@yahoo.co.in
Cheers,
Raviraj
Member for
18 years 4 monthsRE: Problems coverting Microsoft Project schedule to P3
Yes, I would appreciate it if you could send it to me.
Thanks
Member for
20 years 4 monthsRE: Problems coverting Microsoft Project schedule to P3
I wrote a procedure for converting if you still need assistancewith this.
Member for
18 years 9 monthsRE: Problems coverting Microsoft Project schedule to P3
Swapna,
MPX format reflects a status of scheduling about 20 years ago. I suppose, you used some features in MSP which are not covered by MPX.
If you have P3e/P5 as well. there is a much simpler way: You switch-off "resource-driven" and switch on "ignore resource calendar" in MSP --> import MPP into P3e ---> schedule and check dates (mostly the MSP-calendar was not maintained) --> Export to P3.
Regards
Dieter