Correct Defination of Level 1,2,3,4 in P3

Member for

18 years 6 months

And this time with spelling that is slightly better.......



Vijayendra,



Try looking on the Planning Engineers Organisation website.



A paper written by Gary France states what should be included in the different levels of a programme.



Regards,



Oliver

Member for

18 years 6 months

Vijayendra,



Try looking on the Planning Engineers Organisation website.



A paper written by Gary France states what should be included in the different keveks of a programme.



Regards,



Oliver

Member for

21 years 4 months

Vijayendra,



Fully agree with Dieter about asking 5 people and getting 10 different answers.



I am someone who would like to add something:



1.- Dieter definition is OK for me. I have minor differences that it might be worthless to mention them.



Key things for me are:



Level 1: I try to define Level 1 in alignment with Project manager and Client. My last 3 projects, The Client gave me the Key Milestones as an input.

At this level I show the Critical Long lead Items (Equipment with critical delivery Time). Very important nowadays with a overheated market.



Lev. 4: must represent the scope of work. It depends on Project phase, for instance:

Engineering: activities defined according list of deliverables.

Procurement: Detailed procurement cycle. Especial attention to split activities when they have different responsible (especially if Client review/approval is involved).



Construction: always construction in a nightmare for me. If the Construction team has a good planning background, I work with a lot of detail especially for every Construction package.

If the Construction team does not have idea of planning, I develop a simple schedule more oriented on the progress measurement database.



Level 2, 3 : It is the roll-up of level 4 in order to inform intermediate management, for instance , Engineering leads, Peocurement leads.



Cheers

Member for

18 years 9 months

Vijayendra

there is no exact definition just a rough common understanding:

L 1: Management overview, i.e. Key milestones + key-hammocks; about 10 activities with baseline

L 2: Still an overview but more detailed: e.g. inclusive lead-time for key items, more milestones; still 40-50 activities, depending on size, importance, risk, ... of the project up to 100.

L 3: All main activities.

L 4: All activities for a certain topic, e.g. all engineering documents



BUT if you’ll ask 5 people you’ll probably get at least 10 answers - basically the same, different in details. --> Levels must be defined with the customer.



In P3 it is very easy:

Create activity-code e.g. "Level Schedule" with the different levels -->

Assign a value to each activity -->

Create filters for each -->

Arrange page setup for each -->

Create layout for each -->

give a proper name -->

save



If a collegue did so already, with the transfer button you can easily copy those filters and layouts - access rights assumed.



Regards



Dieter