How to link schedules?

Member for

20 years 7 months

hello,



"Interproject Relationships" is what you are looking for.



password: INTRPROJ



it is located under:



P3PROGS\INTRPROJ.EXE



please read the related help files BEFORE doing any changes.

Always write the changes down, link between milestones clearly defined as "linked/from". If you don’t do this, after some time, you will forget they are there and wonder (possibly spending hours in the process) why the schedule is acting weird.



hope this helps.



Gün :)

Member for

19 years 5 months

Hi,



thank you for your reply. I want to create a hammock activity in one program then to link this activity to an external program. My purpose is to reduce the number of activities of the program that I submit to the Engineer Representative. "Interproject" offers the option to link 2 programs with a FS link. I will keep trying and let you know.



Regards,

Member for

18 years 5 months

Hi Ghassan,

Do you mean reduce the number of activities by linking to your other schedules and thus reducing repetition?

If so can your other schedules be sub-projects and then link with milestones, I haven’t used/considered a hammock but the milestones work well.

Cheers.

Karen

Member for

22 years 8 months

If they are sub-projects of the same project group this isnt a problem.



I have never tried to use interproj for hammocks, but i imagine it wouldnt work.