i presumed the calculations are linear, please note of your planning unit first, if it is in Day or Hour; then your resource budget quantity; also note that your budget quatity will be distributed linearly; so whether or not you use "each" or hour, expect that it will be calculated linearly, so its up to you to determine which one is workable!
Member for
20 years 7 monthsRE: Loading of resources
Dear Anoon,
Ah ok, Thank you very much for your quick reply.
Regards,
Rick
Member for
19 years 1 monthRE: Loading of resources
i presumed the calculations are linear, please note of your planning unit first, if it is in Day or Hour; then your resource budget quantity; also note that your budget quatity will be distributed linearly; so whether or not you use "each" or hour, expect that it will be calculated linearly, so its up to you to determine which one is workable!