Primavera Project Planner - P3 Member for 24 years 6 months Member for 24 years 7 months Submitted by Paul Harris on Mon, 2007-06-18 11:15 Permalink RE: MPP to P3 A WBS activity spans the duration of all activities with the same WBS code. It is not intended to assign relationships to a WBS activity. Paul E Harris Eastwood Harris Pty Ltd, Melbourne, Australia Planning and Scheduling Training Manual & Book Publishers & Consulting www.eh.com.au Log in or register to post comments
Member for 24 years 6 months Member for 24 years 7 months Submitted by Paul Harris on Mon, 2007-06-18 11:15 Permalink RE: MPP to P3 A WBS activity spans the duration of all activities with the same WBS code. It is not intended to assign relationships to a WBS activity. Paul E Harris Eastwood Harris Pty Ltd, Melbourne, Australia Planning and Scheduling Training Manual & Book Publishers & Consulting www.eh.com.au
Member for
24 years 6 monthsRE: MPP to P3
A WBS activity spans the duration of all activities with the same WBS code. It is not intended to assign relationships to a WBS activity.
Paul E Harris
Eastwood Harris Pty Ltd, Melbourne, Australia
Planning and Scheduling Training Manual & Book Publishers & Consulting
www.eh.com.au