Primavera Project Planner - P3 Member for 19 years 4 months Member for 19 years 5 months Submitted by Nicolas Berger on Tue, 2007-06-12 13:28 Permalink RE: Global change for Lags... Yes I know but we were wondering if it might be possible using the global change... Member for 20 years 11 months Member for 20 years 11 months Submitted by Andrew Podolny on Tue, 2007-06-12 09:14 Permalink RE: Global change for Lags... Use Import / Export (Activity ID, Logs) instead of Global Change. Regards Andrew Log in or register to post comments
Member for 19 years 4 months Member for 19 years 5 months Submitted by Nicolas Berger on Tue, 2007-06-12 13:28 Permalink RE: Global change for Lags... Yes I know but we were wondering if it might be possible using the global change...
Member for 20 years 11 months Member for 20 years 11 months Submitted by Andrew Podolny on Tue, 2007-06-12 09:14 Permalink RE: Global change for Lags... Use Import / Export (Activity ID, Logs) instead of Global Change. Regards Andrew
Member for
19 years 4 monthsRE: Global change for Lags...
Yes I know but we were wondering if it might be possible using the global change...
Member for
20 years 11 monthsRE: Global change for Lags...
Use Import / Export (Activity ID, Logs) instead of Global Change.
Regards
Andrew