P3 3.0 Calendar

Member for

18 years 7 months

Thanks Ashraf and Pranab for your help.



So Stupid of me. When I copied my Project I did not put any attention to Planning Unit details that was set on Months. So, I had to copied it back with Planning Unit as DAYS and it is back to normal.



CHEERS

Member for

18 years 6 months

Ahmed,



Bit strage, if it is for the running projects that you are working on. However if this problem is with new project then try to transfer calendar from the existing project.



Regards,



Ashraf

Member for

18 years 9 months

Hello Ahmed,

I feel this will restore the issue

Double click the Date Line( Time Scale ) , the time scale bar will pop > click calender dates and minimum time unit days

regards

deb