So Stupid of me. When I copied my Project I did not put any attention to Planning Unit details that was set on Months. So, I had to copied it back with Planning Unit as DAYS and it is back to normal.
CHEERS
Member for
18 years 6 months
Member for18 years6 months
Submitted by Ashraf Jahangeer on Sat, 2007-06-02 08:53
Bit strage, if it is for the running projects that you are working on. However if this problem is with new project then try to transfer calendar from the existing project.
Regards,
Ashraf
Member for
18 years 9 months
Member for18 years9 months
Submitted by Pranab Kumar Deb on Sat, 2007-06-02 08:53
Member for
18 years 7 monthsRE: P3 3.0 Calendar
Thanks Ashraf and Pranab for your help.
So Stupid of me. When I copied my Project I did not put any attention to Planning Unit details that was set on Months. So, I had to copied it back with Planning Unit as DAYS and it is back to normal.
CHEERS
Member for
18 years 6 monthsRE: P3 3.0 Calendar
Ahmed,
Bit strage, if it is for the running projects that you are working on. However if this problem is with new project then try to transfer calendar from the existing project.
Regards,
Ashraf
Member for
18 years 9 monthsRE: P3 3.0 Calendar
Hello Ahmed,
I feel this will restore the issue
Double click the Date Line( Time Scale ) , the time scale bar will pop > click calender dates and minimum time unit days
regards
deb