S Curve - P3

Member for

20 years 2 months

Hi jaya,



You made mention you have already allocated resoucres and cost to your schedule. to find s- curve more easy in tracking your progress, all you have to do firstly is to create a baseline to compare it to your current schedule which is data date. then in primavera p3 in tool menu,graphic, click resource & cost .if you want to see the overall cost or resource curve you may just type the command string as ?????? to the selection. However in Primavera P5 you may treat it in a dirrent way but basically homologous in nature. just go to Click menu Project, Tracking layout, resource usage then activity profile option, and set up your printing preferences to view your s-curve.



Uly

Member for

18 years 9 months

DEAR ASHRAF AND AHMED,

THANK YOU BOTH FOR THE HELP

REGARDS

DEB

Member for

18 years 7 months

Thanks Ashraf for your valuable tip.

Infact, I also encountered the same problem as Parnab. But, then I changed the syntax with ADD and it worked fine.

Cheers

Member for

18 years 7 months

Hi Parnab

Just a little change in Ashraf’s syntax

Resouce +(ADD) R

rather EQ

Member for

18 years 6 months

Try this Deb,



1. Add Resource

If OD > 0 the RES AD R



Regards,



Ashraf

Member for

18 years 9 months

hello ashraf i have done exactly as per your advice still it is not working , when i run 1 , it say no activities affected

regards

deb

Member for

18 years 6 months

Define the following Global Change.





1. Add Resource

If OD > 0 the Resourse = R



2. Modify Resurce



If OD > 0 then RDUR = OD





First run 1 and then run 2.



Regards,



Ashraf






Member for

18 years 9 months

hello ashraf but i am unable to assign this resource r to all activities

regards

deb

Member for

19 years 3 months

In MSP, to find the same..I will auto update the project keeping the data date as project end date considering all the activities are happened as well as planned..



After this, I can take the S - curve / Monthly progress happened from the Reports and will plot the S-Curve...But any option, like that wud available in P3



J

Member for

19 years 3 months

oops...I did it....



Ashraf and Bijaya....Thank u...Thank u very much



It worked well...



J

Member for

20 years 8 months

S curve for what? Usually you will use it for resource (number or cost), or cost. If you don’t have those parameters in the programme and you still wish to see S curve, you need to think of something - and original duration as suggested by Ashraf is a very good idea. Just think of Original duration as a resource.



You can make an even simpler S curve. If you give your activty 1 point for starting and 1 point for finishing, you have two points each planned for every activity. In a number of occasions, even such an S curve comes as a very good project control tool. Now to get this curve in P3, you, of course need to create a resource S. You can then globally assign 2 units of it to all the activities.

Member for

19 years 3 months

Dear Ashraf,



Thanks for ur reply....



T s not clear,,,am not convinced....can u explain this or is there any other way available...



J

Member for

18 years 6 months

Jaya,



Define a resource named R.



Run Global change and add R to all activities.



Then run a global change Resource R = OD.



You can now get the desired S-Curves which will be based on OD.



Regards,



Ashraf