You made mention you have already allocated resoucres and cost to your schedule. to find s- curve more easy in tracking your progress, all you have to do firstly is to create a baseline to compare it to your current schedule which is data date. then in primavera p3 in tool menu,graphic, click resource & cost .if you want to see the overall cost or resource curve you may just type the command string as ?????? to the selection. However in Primavera P5 you may treat it in a dirrent way but basically homologous in nature. just go to Click menu Project, Tracking layout, resource usage then activity profile option, and set up your printing preferences to view your s-curve.
Uly
Member for
18 years 9 months
Member for18 years9 months
Submitted by Pranab Kumar Deb on Sat, 2007-06-02 06:24
In MSP, to find the same..I will auto update the project keeping the data date as project end date considering all the activities are happened as well as planned..
After this, I can take the S - curve / Monthly progress happened from the Reports and will plot the S-Curve...But any option, like that wud available in P3
J
Member for
19 years 3 months
Member for19 years3 months
Submitted by J Venkatesh PM… on Tue, 2007-05-22 10:31
S curve for what? Usually you will use it for resource (number or cost), or cost. If you dont have those parameters in the programme and you still wish to see S curve, you need to think of something - and original duration as suggested by Ashraf is a very good idea. Just think of Original duration as a resource.
You can make an even simpler S curve. If you give your activty 1 point for starting and 1 point for finishing, you have two points each planned for every activity. In a number of occasions, even such an S curve comes as a very good project control tool. Now to get this curve in P3, you, of course need to create a resource S. You can then globally assign 2 units of it to all the activities.
Member for
19 years 3 months
Member for19 years3 months
Submitted by J Venkatesh PM… on Mon, 2007-05-21 10:42
Member for
20 years 2 monthsRE: S Curve - P3
Hi jaya,
You made mention you have already allocated resoucres and cost to your schedule. to find s- curve more easy in tracking your progress, all you have to do firstly is to create a baseline to compare it to your current schedule which is data date. then in primavera p3 in tool menu,graphic, click resource & cost .if you want to see the overall cost or resource curve you may just type the command string as ?????? to the selection. However in Primavera P5 you may treat it in a dirrent way but basically homologous in nature. just go to Click menu Project, Tracking layout, resource usage then activity profile option, and set up your printing preferences to view your s-curve.
Uly
Member for
18 years 9 monthsRE: S Curve - P3
DEAR ASHRAF AND AHMED,
THANK YOU BOTH FOR THE HELP
REGARDS
DEB
Member for
18 years 7 monthsRE: S Curve - P3
Thanks Ashraf for your valuable tip.
Infact, I also encountered the same problem as Parnab. But, then I changed the syntax with ADD and it worked fine.
Cheers
Member for
18 years 7 monthsRE: S Curve - P3
Hi Parnab
Just a little change in Ashrafs syntax
Resouce +(ADD) R
rather EQ
Member for
18 years 6 monthsRE: S Curve - P3
Try this Deb,
1. Add Resource
If OD > 0 the RES AD R
Regards,
Ashraf
Member for
18 years 9 monthsRE: S Curve - P3
hello ashraf i have done exactly as per your advice still it is not working , when i run 1 , it say no activities affected
regards
deb
Member for
18 years 6 monthsRE: S Curve - P3
Define the following Global Change.
1. Add Resource
If OD > 0 the Resourse = R
2. Modify Resurce
If OD > 0 then RDUR = OD
First run 1 and then run 2.
Regards,
Ashraf
Member for
18 years 9 monthsRE: S Curve - P3
hello ashraf but i am unable to assign this resource r to all activities
regards
deb
Member for
19 years 3 monthsRE: S Curve - P3
In MSP, to find the same..I will auto update the project keeping the data date as project end date considering all the activities are happened as well as planned..
After this, I can take the S - curve / Monthly progress happened from the Reports and will plot the S-Curve...But any option, like that wud available in P3
J
Member for
19 years 3 monthsRE: S Curve - P3
oops...I did it....
Ashraf and Bijaya....Thank u...Thank u very much
It worked well...
J
Member for
20 years 8 monthsRE: S Curve - P3
S curve for what? Usually you will use it for resource (number or cost), or cost. If you dont have those parameters in the programme and you still wish to see S curve, you need to think of something - and original duration as suggested by Ashraf is a very good idea. Just think of Original duration as a resource.
You can make an even simpler S curve. If you give your activty 1 point for starting and 1 point for finishing, you have two points each planned for every activity. In a number of occasions, even such an S curve comes as a very good project control tool. Now to get this curve in P3, you, of course need to create a resource S. You can then globally assign 2 units of it to all the activities.
Member for
19 years 3 monthsRE: S Curve - P3
Dear Ashraf,
Thanks for ur reply....
T s not clear,,,am not convinced....can u explain this or is there any other way available...
J
Member for
18 years 6 monthsRE: S Curve - P3
Jaya,
Define a resource named R.
Run Global change and add R to all activities.
Then run a global change Resource R = OD.
You can now get the desired S-Curves which will be based on OD.
Regards,
Ashraf