You could have a different calendar id for that activity, where you define the holiday periods. Then go to format => bars => early bars => check box for "neck" and "holidays". Good luck.
Member for
18 years 6 months
Member for18 years6 months
Submitted by Ashraf Jahangeer on Sun, 2007-05-13 09:54
Member for
18 years 9 monthsRE: How to show suspended activity in the bar chart
You could have a different calendar id for that activity, where you define the holiday periods. Then go to format => bars => early bars => check box for "neck" and "holidays". Good luck.
Member for
18 years 6 monthsRE: How to show suspended activity in the bar chart
Hi Mark,
It was an interesting excercise however I tried one solution which may suit you.
You can define a seperate calender for the above actvity and show the days as non working for as many days as you like to suspend it.
Regards,
Ashraf