Primavera Project Planner - P3 Member for 21 years Member for 21 years Submitted by David Moses on Fri, 2007-05-11 11:15 Permalink RE: Actual activity drives its succcessor Hi There, On your case, If you run the schedule, you will see some messages like, a) Activity started, predecessor has not finished. b) Activity started too early to allow it to finish after the expiration of its predecessors lag. etc. etc... on the Scheduling Report Page. That means there are some relationship problems on your current schedule. Solution: 1) Ignore it 2) If your client accepts, change those activities relationship logic. Regards, Member for 18 years 7 months Member for 18 years 7 months Submitted by OSMAN CERAN on Fri, 2007-05-11 06:21 Permalink RE: Actual activity drives its succcessor Rey Thank you very much! Osman Member for 19 years 8 months Member for 19 years 8 months Submitted by Rey Basadre on Fri, 2007-05-11 05:11 Permalink RE: Actual activity drives its succcessor Osman, Re-schedule and/or modify the link between those activities to reflect the current status/situation, or use Progress Override option. Rey Log in or register to post comments
Member for 21 years Member for 21 years Submitted by David Moses on Fri, 2007-05-11 11:15 Permalink RE: Actual activity drives its succcessor Hi There, On your case, If you run the schedule, you will see some messages like, a) Activity started, predecessor has not finished. b) Activity started too early to allow it to finish after the expiration of its predecessors lag. etc. etc... on the Scheduling Report Page. That means there are some relationship problems on your current schedule. Solution: 1) Ignore it 2) If your client accepts, change those activities relationship logic. Regards,
Member for 18 years 7 months Member for 18 years 7 months Submitted by OSMAN CERAN on Fri, 2007-05-11 06:21 Permalink RE: Actual activity drives its succcessor Rey Thank you very much! Osman
Member for 19 years 8 months Member for 19 years 8 months Submitted by Rey Basadre on Fri, 2007-05-11 05:11 Permalink RE: Actual activity drives its succcessor Osman, Re-schedule and/or modify the link between those activities to reflect the current status/situation, or use Progress Override option. Rey
Member for
21 yearsRE: Actual activity drives its succcessor
Hi There,
On your case,
If you run the schedule, you will see some messages like,
a) Activity started, predecessor has not finished.
b) Activity started too early to allow it to finish after the expiration of its predecessors lag.
etc. etc... on the Scheduling Report Page.
That means there are some relationship problems on your current schedule.
Solution:
1) Ignore it
2) If your client accepts, change those activities relationship logic.
Regards,
Member for
18 years 7 monthsRE: Actual activity drives its succcessor
Rey
Thank you very much!
Osman
Member for
19 years 8 monthsRE: Actual activity drives its succcessor
Osman,
Re-schedule and/or modify the link between those activities to reflect the current status/situation, or use Progress Override option.
Rey