Hi There,



On your case,



If you run the schedule, you will see some messages like,



a) Activity started, predecessor has not finished.

b) Activity started too early to allow it to finish after the expiration of its predecessor’s lag.



etc. etc... on the Scheduling Report Page.



That means there are some relationship problems on your current schedule.



Solution:

1) Ignore it

2) If your client accepts, change those activities relationship logic.



Regards,

Member for

19 years 8 months

Osman,



Re-schedule and/or modify the link between those activities to reflect the current status/situation, or use Progress Override option.



Rey