Primavera Project Planner - P3 Member for 19 years Member for 19 years Submitted by Rodel Marasigan on Wed, 2007-05-09 16:36 Permalink RE: Format chart to show weekdays and weekends Hi Terry, Format Bar then tick Neck on the bars that you want to show the necking and also tick "also neck for" Holiday and Weekends. Rodel Log in or register to post comments
Member for 19 years Member for 19 years Submitted by Rodel Marasigan on Wed, 2007-05-09 16:36 Permalink RE: Format chart to show weekdays and weekends Hi Terry, Format Bar then tick Neck on the bars that you want to show the necking and also tick "also neck for" Holiday and Weekends. Rodel
Member for
19 yearsRE: Format chart to show weekdays and weekends
Hi Terry,
Format Bar then tick Neck on the bars that you want to show the necking and also tick "also neck for" Holiday and Weekends.
Rodel