I will not input pc% = 100% for an activity if its cancelled. Id rather create a planning level for cancelled activities and apply it to activities i want to cancel. Then in the cost report format, I will add a selection criteria to exclude all cancelled acitivities. Hope this helps..Maybe someone else will have a better idea. Cheers..
Member for
18 years 9 monthsRE: cost control
Hi Forat,
I will not input pc% = 100% for an activity if its cancelled. Id rather create a planning level for cancelled activities and apply it to activities i want to cancel. Then in the cost report format, I will add a selection criteria to exclude all cancelled acitivities. Hope this helps..Maybe someone else will have a better idea. Cheers..
Ifeanyi