Hi Forat,



I will not input pc% = 100% for an activity if it’s cancelled. I’d rather create a planning level for cancelled activities and apply it to activities i want to cancel. Then in the cost report format, I will add a selection criteria to exclude all cancelled acitivities. Hope this helps..Maybe someone else will have a better idea. Cheers..



Ifeanyi