P3 Planned vs actual

Member for

20 years 8 months

P3 makes S curve from resource data. So the first question to you is whether your programme is resource loaded?



I know you are just trying to compare planned percent complete vs actual percent. But the "percent complete" on its own can mean a lot of things to lot of people. And as for S curves in P3, percent complete is derived either from units or costs of the resources.