P3 TO EXCEL... URGENT

Member for

18 years 11 months

Summary activities can also be made as "WBS type" activities and exported as normal activities to excel. That is of course if you use wbs structure in your project and not only coding

Member for

19 years 8 months

To transfer summary tasks with activites:



Activity codes should be exported with activities.



then you can finalized in Excel.



Essam Rushdi

Member for

23 years 10 months



Try use the following function.



=min( ) for start date



and



=max( ) for finish date.



Amri

Member for

20 years 6 months

Your "summary tasks" are not in fact tasks at all, but just the organisational summaries. They cannot be exported.

Member for

19 years 1 month

Thank you for quick reply.

With the guidance of you I figured out p3 to excel . But still I am unable to transfer summary tasks with activites.

Is it possible? to transfer summary task with activities??

Member for

19 years

Tools/Project Utility/Export...

select WHAT u wnat to export

remember to export in WK1 format.



MS Excel can open WK1 files.



but read in a thread that says MS Excel 2007 CANNOT open wk1.