How to Generate S Curve after resource Loading in P3???

Member for

14 years 8 months

Can any body tell how to load a resource and prepare resource loading schedule,

indirect labour schedule and direct labour schedule?

plz help me .if its long answer plz tell me the refrence.

Member for

18 years 9 months

i fully agree with Bijaya , search option in planning planet will definitely help planners to have exactly the information that they are looking to else a lot of hard work by senior planners are wasted.

regards

deb

Member for

20 years 8 months

If you have resource loaded your activities, you have done the most time consuming part. In fact the S curve is already there now - and what you need to how to view it.



Press the button "Resource/cost profile" which usually appear on to with bar chart icon on top. If you don’t see it, just go to View and then Ressource Profile.



You will see the profile at the bottom of the screen. Click "Display" button and then choose curve. If you also want histogram, choose that as well.



There are various filters and selection you can then apply depending on your need.



Good luck