Primavera Project Planner - P3 Member for 18 years 10 months Member for 18 years 10 months Submitted by Ahmed Nabil on Thu, 2007-03-22 11:06 Permalink RE: re-occuring activities I am not sure if that what u want but i will just put it in case 1- add another calender with all stops that u want 2- assign this calender to this activity Member for 18 years 9 months Member for 18 years 9 months Submitted by Jonathan Ward on Thu, 2007-03-22 09:16 Permalink RE: re-occuring activities ,, i will creat a calendar for that activity to stop work for two weeks then re-commence Log in or register to post comments
Member for 18 years 10 months Member for 18 years 10 months Submitted by Ahmed Nabil on Thu, 2007-03-22 11:06 Permalink RE: re-occuring activities I am not sure if that what u want but i will just put it in case 1- add another calender with all stops that u want 2- assign this calender to this activity
Member for 18 years 9 months Member for 18 years 9 months Submitted by Jonathan Ward on Thu, 2007-03-22 09:16 Permalink RE: re-occuring activities ,, i will creat a calendar for that activity to stop work for two weeks then re-commence
Member for
18 years 10 monthsRE: re-occuring activities
I am not sure if that what u want
but i will just put it in case
1- add another calender with all stops that u want
2- assign this calender to this activity
Member for
18 years 9 monthsRE: re-occuring activities
,, i will creat a calendar for that activity to stop work for two weeks then re-commence