You need to organize your project by predecessor or successor and you may display the predecessor or successors, the relationship type and the lag in columns, then cut and paste to Excel.
Any data that may be displayed in columns may be cut and pasted to Excel. SureTrak also has a pivot table export script that now works properly with the Service Pack 3, which will export time phased data, all be it slowly.
You may also run a Predecessor and Successor softbridge script which will give you all relationship detail in a text file that may be manipulated with Data, Text to columns in Excel.
It is also possible to assign the same resource multiple times to an activity in SureTrak with its own lag and duration. To do this in P3 each resource assignment needs to be unique by assigning a different a Resource Curve or Cost account.
Paul E Harris
Eastwood Harris Pty Ltd, Melbourne, Australia
Planning and Scheduling Training Manual & Book Publishers & Consulting
Member for
24 years 6 monthsRE: Suretrak - Export Resource Lag
You need to organize your project by predecessor or successor and you may display the predecessor or successors, the relationship type and the lag in columns, then cut and paste to Excel.
Any data that may be displayed in columns may be cut and pasted to Excel. SureTrak also has a pivot table export script that now works properly with the Service Pack 3, which will export time phased data, all be it slowly.
You may also run a Predecessor and Successor softbridge script which will give you all relationship detail in a text file that may be manipulated with Data, Text to columns in Excel.
It is also possible to assign the same resource multiple times to an activity in SureTrak with its own lag and duration. To do this in P3 each resource assignment needs to be unique by assigning a different a Resource Curve or Cost account.
Paul E Harris
Eastwood Harris Pty Ltd, Melbourne, Australia
Planning and Scheduling Training Manual & Book Publishers & Consulting
www.eh.com.au