export and import process from MS Project to P3 has still some bugs, you will be surprised to see everything imported to P3 but when you time analyzed the programme some activites are not moving according to their logic or relationship.
It would save you time if copy and paste the activity ID, Description and Duration rather than retyping it manually onto P3. (and) The rest has to be rebuild on P3 (e.g. link and resources)
Member for
24 years 6 monthsRE: export&import exel to P3
There is a paper on my web site which explains this process.
Paul E Harris
Eastwood Harris Pty Ltd, Melbourne, Australia
Planning and Scheduling Training Manual & Book Publishers & Consulting
www.eh.com.au
Member for
18 years 8 monthsRE: export&import exel to P3
export and import process from MS Project to P3 has still some bugs, you will be surprised to see everything imported to P3 but when you time analyzed the programme some activites are not moving according to their logic or relationship.
It would save you time if copy and paste the activity ID, Description and Duration rather than retyping it manually onto P3. (and) The rest has to be rebuild on P3 (e.g. link and resources)