In my opinion , you should add a resources called weight value to your project. The BQ for any perticular activity will be same as ( or multiple of any constant like 100, 1000,.. etc as per your convenience ), what weight value you want to assigned that perticulat activity.
Make sure that all the required link is marked in Auto cost rule, so that p3 will calculate the actual to date & actual this period as per OD & RD.
As, Mr Karim said, it will be updated automatically in regards of Actual to date, To complete....etc after each updates, and u can produce your reports in terms of desired weight value.
thanks,
Prabin Kumar
Member for
19 years 7 months
Member for19 years7 months
Submitted by Karim Mounir on Sat, 2007-02-10 00:22
You can make a dummy resource (for example called "activity days"), then assign all of your activities with this resource.
The BQ of this resource will be equal to the OD of each activity.
After that when u update your schedule, the actual units will be updated automatically which will give u the overall actual progress % (u can generate a tabular report for this).
Member for
18 years 9 monthsRE: Activity weight
thank you Mr Karim Mounir and Karim Mounir
perfect answer
Member for
20 years 1 monthRE: Activity weight
In my opinion , you should add a resources called weight value to your project. The BQ for any perticular activity will be same as ( or multiple of any constant like 100, 1000,.. etc as per your convenience ), what weight value you want to assigned that perticulat activity.
Make sure that all the required link is marked in Auto cost rule, so that p3 will calculate the actual to date & actual this period as per OD & RD.
As, Mr Karim said, it will be updated automatically in regards of Actual to date, To complete....etc after each updates, and u can produce your reports in terms of desired weight value.
thanks,
Prabin Kumar
Member for
19 years 7 monthsRE: Activity weight
You can make a dummy resource (for example called "activity days"), then assign all of your activities with this resource.
The BQ of this resource will be equal to the OD of each activity.
After that when u update your schedule, the actual units will be updated automatically which will give u the overall actual progress % (u can generate a tabular report for this).