remainging duration

Member for

19 years

Dear Mohammad

I already try this option but not working. Thanks for reply. I found the mistake there is some mistake in logic that why the remaining duration was calculate after the FS of predessor activity where as this should be FF with a counted lag.

Thanks again for quick reply.

Regard

Tahir

Member for

19 years 1 month

Hi,



To update separately the remaining duration & the activity % comp. Just uncheck from the auto cost rule "Link remaining duration & schedule percent complete"



But then you have to update remaining duration for all the schedule activities manually.



Regards,



Moe