Primavera Project Planner - P3 Member for 22 years 8 months Member for 22 years 9 months Submitted by Alex Wong on Fri, 2006-10-27 00:02 Permalink RE: line showing the project completion date in the Bar cha Gents You can also display what we call the activity progress line in the bar chart to indicate any ahead and delay progress Alex Member for 23 years Member for 23 years Submitted by Steven Oliver on Thu, 2006-10-26 04:58 Permalink RE: line showing the project completion date in the Bar cha Have a look in the Help, for "Curtain". From memory, the curtain toolbar is accessed from View, Attachments. Log in or register to post comments
Member for 22 years 8 months Member for 22 years 9 months Submitted by Alex Wong on Fri, 2006-10-27 00:02 Permalink RE: line showing the project completion date in the Bar cha Gents You can also display what we call the activity progress line in the bar chart to indicate any ahead and delay progress Alex
Member for 23 years Member for 23 years Submitted by Steven Oliver on Thu, 2006-10-26 04:58 Permalink RE: line showing the project completion date in the Bar cha Have a look in the Help, for "Curtain". From memory, the curtain toolbar is accessed from View, Attachments.
Member for
22 years 8 monthsRE: line showing the project completion date in the Bar cha
Gents
You can also display what we call the activity progress line in the bar chart to indicate any ahead and delay progress
Alex
Member for
23 yearsRE: line showing the project completion date in the Bar cha
Have a look in the Help, for "Curtain".
From memory, the curtain toolbar is accessed from View, Attachments.