resource levelling

Member for

21 years 5 months

John



Have you tried dividing by 8 or 40, and showing the time window in days or weeks?



Hope this helps

John R

Member for

24 years 6 months

There are a couples place in P3 where there is a 9999 limit including activity duraton which restricts the total duration of a project.



Paul E Harris

Eastwood Harris Pty Ltd, Melbourne, Australia

Planning and Scheduling Training Manual & Book Publishers & Consulting

www.eh.com.au

Member for

21 years

John,



I’ve always just divided the resource requirement and the resource availablity by a factor of 10.