Primavera Project Planner - P3 Member for 21 years 5 months Member for 21 years 5 months Submitted by John Raper on Thu, 2006-10-05 09:57 Permalink RE: resource levelling John Have you tried dividing by 8 or 40, and showing the time window in days or weeks? Hope this helps John R Member for 24 years 6 months Member for 24 years 7 months Submitted by Paul Harris on Thu, 2006-10-05 08:19 Permalink RE: resource levelling There are a couples place in P3 where there is a 9999 limit including activity duraton which restricts the total duration of a project. Paul E Harris Eastwood Harris Pty Ltd, Melbourne, Australia Planning and Scheduling Training Manual & Book Publishers & Consulting www.eh.com.au Member for 21 years Member for 21 years Submitted by David Kelly on Thu, 2006-10-05 05:40 Permalink RE: resource levelling John, Ive always just divided the resource requirement and the resource availablity by a factor of 10. Log in or register to post comments
Member for 21 years 5 months Member for 21 years 5 months Submitted by John Raper on Thu, 2006-10-05 09:57 Permalink RE: resource levelling John Have you tried dividing by 8 or 40, and showing the time window in days or weeks? Hope this helps John R
Member for 24 years 6 months Member for 24 years 7 months Submitted by Paul Harris on Thu, 2006-10-05 08:19 Permalink RE: resource levelling There are a couples place in P3 where there is a 9999 limit including activity duraton which restricts the total duration of a project. Paul E Harris Eastwood Harris Pty Ltd, Melbourne, Australia Planning and Scheduling Training Manual & Book Publishers & Consulting www.eh.com.au
Member for 21 years Member for 21 years Submitted by David Kelly on Thu, 2006-10-05 05:40 Permalink RE: resource levelling John, Ive always just divided the resource requirement and the resource availablity by a factor of 10.
Member for
21 years 5 monthsRE: resource levelling
John
Have you tried dividing by 8 or 40, and showing the time window in days or weeks?
Hope this helps
John R
Member for
24 years 6 monthsRE: resource levelling
There are a couples place in P3 where there is a 9999 limit including activity duraton which restricts the total duration of a project.
Paul E Harris
Eastwood Harris Pty Ltd, Melbourne, Australia
Planning and Scheduling Training Manual & Book Publishers & Consulting
www.eh.com.au
Member for
21 yearsRE: resource levelling
John,
Ive always just divided the resource requirement and the resource availablity by a factor of 10.