To view in Layout you will need to go into "Page Setup" and tick the box "Resource/Cost Dispay".
The layout will display the Histogramme / Curve at the bottom of the schedule. It is verry effective for a high level plan especially if displayed on a single sheet.
To get the data as you require you need to use the "select" and "dispay" buttons, can be a bit of a problem when first setting up.
Q1 : How do I extract data from P3 (or let P3 generate) to create S-Curve.?
Try: Tools / Tabular Reports / Resource / Loading
You will need to set up the P3 window options with your resources / selection etc. Once run it will generate a stread sheet format that you can make into SCurve / Histogram etc, and save as excel format etc
Or try: Tools / Tabular Reports / Resource / Tabular
This will give you a hard copy of data, that you will need to key into a Curve etc.
Q3 - Paste in Excel & gnerate S-Curve (progress %) as Excel Chart.
Yes - see above - just add calculations to the excel spread sheet.
Q2 : Can P3 do it per WBS/Activity Codes or discipline etc.?
Yes, its all done when you set up the P3 windows, its a bit messy first time, but try using the P3 Help option if you get stuck.
Q3 : How do I generate Manpower Loading (unlevel) in P3.
Use the above, the info generated is in Man hours so just set up your excel spread sheet with a simple calculation.
Member for
21 years 1 monthRE: Generate S-Curve & MPL
Hi
If you check out and follow reply of the 07-Sept..
You should then be able to export the data from P3 in an Excel format.
The data will be by manhours by time period (i.e. how you have specified - weekly/monthly etc).
You then need to add rows etc and set up the standard calculations for working out percentage complete etc.
Regards
John
Member for
22 years 8 monthsRE: Generate S-Curve & MPL
Hi
Try the method suggested by us. That will give you a good S-Curve facility, especailly in Layout View.
Alex
Member for
19 years 10 monthsRE: Generate S-Curve & MPL
I would like to extract percentage completion distributed by time-period from Primavera. Can anybody help me?
Many thanks in advance.
Hashim
Member for
21 years 1 monthRE: Generate S-Curve & MPL
Hi
To view in Layout you will need to go into "Page Setup" and tick the box "Resource/Cost Dispay".
The layout will display the Histogramme / Curve at the bottom of the schedule. It is verry effective for a high level plan especially if displayed on a single sheet.
To get the data as you require you need to use the "select" and "dispay" buttons, can be a bit of a problem when first setting up.
Regards
John
Member for
22 years 8 monthsRE: Generate S-Curve & MPL
Just 2 points as well:
1. You can view the S-Curve in Layout as well (View - Layout)
2. Remember to you save period actuals
Then you S-Curve will have a more accurate result in Earned Value and Actual.
This concept is differ from MSP
Alex
Member for
21 years 1 monthRE: Generate S-Curve & MPL
Hi
Q1 : How do I extract data from P3 (or let P3 generate) to create S-Curve.?
Try: Tools / Tabular Reports / Resource / Loading
You will need to set up the P3 window options with your resources / selection etc. Once run it will generate a stread sheet format that you can make into SCurve / Histogram etc, and save as excel format etc
Or try: Tools / Tabular Reports / Resource / Tabular
This will give you a hard copy of data, that you will need to key into a Curve etc.
Q3 - Paste in Excel & gnerate S-Curve (progress %) as Excel Chart.
Yes - see above - just add calculations to the excel spread sheet.
Q2 : Can P3 do it per WBS/Activity Codes or discipline etc.?
Yes, its all done when you set up the P3 windows, its a bit messy first time, but try using the P3 Help option if you get stuck.
Q3 : How do I generate Manpower Loading (unlevel) in P3.
Use the above, the info generated is in Man hours so just set up your excel spread sheet with a simple calculation.
regards
John