There is a way of doing this in P3. YOu need to set-up P3 to show progress against your target (baseline). Of course you need to show your target bar instead of your current bar. This will show progress against your target without moving the end dates.
Member for
24 years 6 monthsRE: No automatic scheduleding
Andrew,
You can move the data date without scheduling through the Global calendars.
Highlight the Global calendar and click the standard button. Data date is an editable field in this form.
NOTE - if you schedule (press F9) then P3 uses this new date so using a target as discussed below is the better solution.
Not 100% sure what you are doing but thought Id give this option as well
Member for
24 yearsRE: No automatic scheduleding
Andrew,
There is a way of doing this in P3. YOu need to set-up P3 to show progress against your target (baseline). Of course you need to show your target bar instead of your current bar. This will show progress against your target without moving the end dates.
Hope this helps.
Cheers,
Daniel
Member for
21 yearsRE: No automatic scheduleding
andrew,
This cannot be done. The data date cannot be reset without scheduling.
You can use the attachment toolbar to drop a curtain, or a line, or indeed use the progress spotlight to highlight a date range.