No automatic scheduleding

Member for

24 years 6 months

Andrew,



You can move the data date without scheduling through the Global calendars.



Highlight the Global calendar and click the standard button. Data date is an editable field in this form.



NOTE - if you schedule (press F9) then P3 uses this new date so using a target as discussed below is the better solution.



Not 100% sure what you are doing but thought I’d give this option as well

Member for

24 years

Andrew,



There is a way of doing this in P3. YOu need to set-up P3 to show progress against your target (baseline). Of course you need to show your target bar instead of your current bar. This will show progress against your target without moving the end dates.



Hope this helps.



Cheers,

Daniel

Member for

21 years

andrew,



This cannot be done. The data date cannot be reset without scheduling.



You can use the attachment toolbar to drop a curtain, or a line, or indeed use the progress spotlight to highlight a date range.