Import excel - P3

Member for

19 years 5 months

Benoit



The simplest way is to start at new project with the correct start date. Add one activity, "Project Start", as a milestone with the correct date. Add the main codes that you are planning to use.



Now export the project including all fields (All Current). Use this as the basis to import your data. This way you have the correct headings at the top of your sheet.



Copy and paste and then import. All you have to do is add the relationships.



Cheers



Nige