Primavera Project Planner - P3 Member for 19 years 6 months Member for 19 years 6 months Submitted by Dinesh Kumar on Sat, 2006-06-03 10:46 Permalink RE: Resource Histogram - Primavera Project Management Thanks Julie... Member for 20 years Member for 20 years Submitted by Julie Scully on Thu, 2006-06-01 22:20 Permalink RE: Resource Histogram - Primavera Project Management Hi Dinesh You will need to be displaying the histogram in your activities view, then go to Page Setup -> Options -> and check the "Profile" box. If you want to print only the histogram you will need to uncheck all other options. Cheers Julie Log in or register to post comments
Member for 19 years 6 months Member for 19 years 6 months Submitted by Dinesh Kumar on Sat, 2006-06-03 10:46 Permalink RE: Resource Histogram - Primavera Project Management Thanks Julie...
Member for 20 years Member for 20 years Submitted by Julie Scully on Thu, 2006-06-01 22:20 Permalink RE: Resource Histogram - Primavera Project Management Hi Dinesh You will need to be displaying the histogram in your activities view, then go to Page Setup -> Options -> and check the "Profile" box. If you want to print only the histogram you will need to uncheck all other options. Cheers Julie
Member for
19 years 6 monthsRE: Resource Histogram - Primavera Project Management
Thanks Julie...
Member for
20 yearsRE: Resource Histogram - Primavera Project Management
Hi Dinesh
You will need to be displaying the histogram in your activities view, then go to Page Setup -> Options -> and check the "Profile" box. If you want to print only the histogram you will need to uncheck all other options.
Cheers
Julie