I rechecked my schedule. I am using the baseline for BCWS calculation. Also, there is only one target defined. Maybe, there is something else that I might have done wrong because this is my first time generating earned value S-curves using P3.
BCWS comes from the baseline plan, so the current start of the activity is unimportant.
All I can think of as to why it is correct in the Layout and not in the Tabular report is that the Layout always refers to target 1, and Tabular reports can chose Target 1 or 2?
Member for
19 years 5 monthsRE: Progress report using P3
Thank you for your reply David.
I rechecked my schedule. I am using the baseline for BCWS calculation. Also, there is only one target defined. Maybe, there is something else that I might have done wrong because this is my first time generating earned value S-curves using P3.
Member for
21 yearsRE: Progress report using P3
Iftikhar,
BCWS comes from the baseline plan, so the current start of the activity is unimportant.
All I can think of as to why it is correct in the Layout and not in the Tabular report is that the Layout always refers to target 1, and Tabular reports can chose Target 1 or 2?