Progress report using P3

Member for

19 years 5 months

Thank you for your reply David.



I rechecked my schedule. I am using the baseline for BCWS calculation. Also, there is only one target defined. Maybe, there is something else that I might have done wrong because this is my first time generating earned value S-curves using P3.

Member for

21 years

Iftikhar,



BCWS comes from the baseline plan, so the current start of the activity is unimportant.



All I can think of as to why it is correct in the Layout and not in the Tabular report is that the Layout always refers to target 1, and Tabular reports can chose Target 1 or 2?