Primavera Project Planner - P3 Member for 20 years 6 months Member for 20 years 6 months Submitted by Rashid Iqbal on Tue, 2006-03-14 17:43 Permalink RE: Several subprojects with automatic resource shifting Hi, Version 5 could somewhat level the resources on different project based on assigned priorities. Though, in my view the leveling capabilities of that version are not comparable to P3. Regards Rashid Log in or register to post comments
Member for 20 years 6 months Member for 20 years 6 months Submitted by Rashid Iqbal on Tue, 2006-03-14 17:43 Permalink RE: Several subprojects with automatic resource shifting Hi, Version 5 could somewhat level the resources on different project based on assigned priorities. Though, in my view the leveling capabilities of that version are not comparable to P3. Regards Rashid
Member for
20 years 6 monthsRE: Several subprojects with automatic resource shifting
Hi,
Version 5 could somewhat level the resources on different project based on assigned priorities. Though, in my view the leveling capabilities of that version are not comparable to P3.
Regards
Rashid