Resources leveling

Member for

24 years 7 months

A definition of leveling is the delaying of an activity until resources are available.



Therefore by definition if you assign more resources than available then the schedule will not be able to level the task and ignore it.



There are functions available in P3 that allow leveling when the number of resources assigned to a task exceed the number available in the Resource dictionary, these are:



1. Smoothing has three options and Time Constrained uses double the maximum limit.

2. Stretching allow a task to be stretched and therefore reducing the Units per Time period.



Paul E Harris

Eastwood Harris Pty Ltd, Melbourne, Australia

Planning and Scheduling Training Manual & Book Publishers & Consulting

www.eh.com.au