Driving Resources With No Activity Split

Member for

21 years

In essence these activities are not being split by the resource levelling process, but by the scheduling process which you are choosing to drive by resource calendars rather than activity calenders. There is no "contiguos activity" option in Primavera.



If what you are trying to do is provide a schedule which contains only "contiguous" activities, I would suggest that you use a filter which will exclude those activities whose end date transgresses the boundary for contiguos operation.