Merging Schedules w/ Different Planning Units

Member for

20 years 7 months

I guess a Global Change would solve the trick but it wouldn’t apply to ’lags’.



Thanks for the suggestion,



Kashyap

Member for

21 years

There are two reasons why you would merge projects with different planning units.



1) Summary reporting, i.e. the output project does NOT need to be scheduled. In this case the dates that come across for the "mixed" planning unis are correct and the summary project should NOT be scheduled.



2) Further scheduling. A global change will be required to change the durations of either the "daily" or "hourly" activities. This MUST be run before you schedule.