store period performance and critical resources

Member for

20 years

Regarding store period performance....



what i undersood here it is..



it stores historical data... so whenever we do updata and reschedule it ... after that we have to do store period performance.....


Member for

22 years 8 months

sunil



There are sereval thread already in the PP forum detailed the process and meaning of Period Performance. Please seach a bit deeper you will find your answer.



Critical Resource - Resource that is critical to the completion of the project (My explaination)



Different project have different critical resource, sometime it is human being, sometime its material, sometime its machine, sometime its money, sometime is time. As a planner you have to determine with the help from your collegues, ie supervisor, PM, SM, CM, QS ...