If your not satisfied with automatic levelling perhaps you could also do the manual levelling before you try to schedule it... but make sure you back-up your copy first before doing any drastic changes just to make sure..
Cheers!
Christian
Member for
20 years 6 months
Member for20 years7 months
Submitted by Zhang Haixiang on Wed, 2005-11-09 00:06
Member for
22 years 5 monthsRE: levelling of resources
Hello,
If your not satisfied with automatic levelling perhaps you could also do the manual levelling before you try to schedule it... but make sure you back-up your copy first before doing any drastic changes just to make sure..
Cheers!
Christian
Member for
20 years 6 monthsRE: levelling of resources
do leveling after reschedule
Member for
24 years 6 monthsRE: levelling of resources
If you wish the schedule to remain levelled then you should not reschedule it.
Paul E Harris
Eastwood Harris Pty Ltd, Melbourne, Australia
Planning and Scheduling Book Publishers, Training & Consulting
www.eh.com.au