levelling of resources

Member for

22 years 5 months

Hello,



If your not satisfied with automatic levelling perhaps you could also do the manual levelling before you try to schedule it... but make sure you back-up your copy first before doing any drastic changes just to make sure..



Cheers!



Christian

Member for

20 years 6 months

do leveling after reschedule

Member for

24 years 6 months

If you wish the schedule to remain levelled then you should not reschedule it.



Paul E Harris

Eastwood Harris Pty Ltd, Melbourne, Australia

Planning and Scheduling Book Publishers, Training & Consulting

www.eh.com.au