Yes Doroteo... If you don’t mind clarifying your question "How can I show it in P3?"



Do you want to show it graphically? or do you want it in tabular form?..



Regards



Christian

Member for

24 years 9 months

Brennan,

there is such thing as the physical volume (quantity) of work. I suspect that Doroteo asked about this. Physical volume of work can be measured in different units and sometimes it is measured as the quantity of materials (concrete as an example). Different volume units are used on different activities and so what? It does not prevent to estimate the physical quantity of the work for each activity (budgeted, actual, etc.).

Of course there may be many materials that are used on each activity. It is not a problem if to show them in the different columns.

I understood the question - if it can be done in P3?

Maybe Doroteo will clarify if the question was understood.

Regards,

Vladimir

Member for

22 years 8 months

hmmmm is there an echo in here?



helloooooo









hellooo









hello

Member for

20 years 5 months

Hi Doroteo,

Yes, U can create your own calculation to get budget quantities using global change, by creating another column using custom data item.

Member for

22 years 8 months

Hi



When you define a resource you can define its unit of quanitity as well. So you can define as No/Unit/or Hrs.



HTH



Alex

Member for

22 years 8 months

Budget Manhours can be displayed in a column using custom data items.



you wouldnt bother displaying budget quantity of materials in a column due to mixed units.