Deliverables in P3

Member for

22 years 4 months

Contractor is only responsible to load the deliverables of their own concern not any responsibility to load the deliverables in his programs related to the Employer. This is entirely Employer’s responsibility.

Member for

20 years 7 months

As with everything in life it is all about balance. No project could be a success if either party has all the control.



I do however agree that the client/project manager should stick to managing and allow the contractor to determine the program content, provided the contractor can display to the client that he is able to provide valuable management level reporting which will allow him to successfully manage his project.



Jackie

Member for

22 years 8 months

Clive



Well said! Totally agreed !



Cheers



Alex

Member for

22 years 8 months

Gents



IMHO I always refer to the PMBOK for this type of question.



The nine area of Project Management- Hope my memory serve me right

TIME

COST

QUALITY

RESOURCE

CHANGE

PROCUREMENT

RISK

CHANGE

INTEGRATION



Therefore, a P3 schedule can be a tool to assist some of the management of these nine areas.



In some projects, some of the nine areas is already managed externally to the schedule, then why duplicate the information and try the manage everything in one place?? The key is "integration" the last skill to separate between a project director (L6) to a project manager (L5).



How can a project manager to integrate all these information together to manage his/her project.



If the schedule is load with information like key equipments, resources, cost. It will at least help the PM integrate four of the major element, TIME, COST, RESOURCE and PROCUREMENT. This is not an absolut solution, because there are x no of combinations of how to manage all nine areas. The key is all these areas need to be manage during the project and they need to manage in a co-ordinate manner (Integrated)



HTH



Alex

Member for

20 years 2 months

Hi Vanessa,



If you won’t use it, don’t load it. I mean, you can make a schedule in P3 without loading the resources; well, unless you want a resource loaded schedule.



I guess, what you mean by deliverables are the bill of quantities. If so, there’s no need to input it in P3. You’ll need this in calculating the duration, manhours, equipments, and cost once you have the production rates and cost unit rates. You can do these calculations in a spreadsheet.



Regards.

Sen

Member for

20 years 6 months

Hi Vanessa Morris,



It’s up to you or your management/client. for some projects I did not load anything. For some project I load material (e.g. concrete, rebar with unit price to calculate cost).



Before you start, ask yourself a question - what you want to achieve by doing all these?



Sometime scheduling is quite simple, it’s just a way to coordinate ( time, sequence, work space, trades), to make everything go smothly.