changing unit price does not affect on Budgeted Cost ??

Member for

20 years 2 months

again hi,



i have again another problem with unit price .



old unit price = 10(1 year ago)

old bq=1



new unit price=13

new bq=1



at the moment bc must be 1x13=13 but it was 10, when i entered resource dictionary, go to that resource and calculate(unit price at that moment is 13)bc changed from 10 to 13, it is ok what i want BUT!



i have same problem with 120 resources . i don’t want do the same thing(first of all find the problem resouces, go that resources and calculate all of them) . So i hope it must be calculated automatically from somewhere



and my simple question : WHERE IS THAT ? HOW CAN I ?



Thanks to everybodyyy


Member for

20 years 2 months

Hi Alex,



"However Cost to complete is a forecast cost, thats why normally it will NOT CHANGE even you change the unit cost."



NOT CHANGE--> it doesn’t change when unit price is ZERO

but it always change unless its unit price is ZERO

i didn’t understand this situation



When you do the same thing in your projects, do you take the same result with me?



Thanks

Member for

22 years 8 months

onur



Cost to complete is different to Budgeted Cost



Budgeted cost is refer to your Q * cost/unit (autocost rule required)

However Cost to complete is a forecast cost, thats why normally it will not change even you change the unit cost.



Its like maintaining your forecast event the budget had changed. It can change in the autocost rule. HTH



Alex

Member for

20 years 2 months

Hi Oliver,



I found an interesting thing :

If you put NOT zero but close to zero like 0.01 to unit price



When you click calculate button, automatically CTC values ara calculated



BUT! when you put zero to unit price and do the same procedure, CTC values are SAME but unit price CHANGED ?!



Any idea?, what can be the solution?