Total Float

Member for

20 years 10 months

Thanks Sunil...

It cleared all my confussion on scheduling option..

Thats why i tell all my friends to visit Planning Planet...

Cheers I am Happy...

Shiva


Member for

20 years 7 months

Guys,



Check this site www.HTCProjectcontrols.com Eric gives a splendid explaination on this topic under Solution Bulletins.A must see site for all planners.



Sunil

Member for

20 years 8 months

Steven you are right.

Basically, Retained Logic is the preferable method. The planner still can use Progress Override to schedule the work programme but after every update he/she need to do some homework, i.e. link all the out-of-sequence activities to the nearest logical successor (FF + lag or FS +/- lag) to minimise/control the large positive float.



Regards.

Member for

22 years 11 months

IMHO, generally the retained logic option should be used. However there are occasions were operations are not directly related to each other, but all need to be done before moving on to the next stage, and progress override can be used.



It is really up to the skill and knowledge of the planner to decide, there is no definitive answer.





HTH


Member for

20 years 10 months

Yes Suku

I did it. and it gave logical float.

What should be normaly done? I mean scheduling with progress overide or Retain logic?



Any way thaks..

Shiva

Member for

20 years 8 months

Shiva,



It is because of Progress Override. When you choose Progress Override, P3 ignores network logic and allows the activity to progress without delay.



So, change the calculation mode to Retained Logic and reschedule your work programme. You will get the logical float.



Regards.