Project Group & Targets

Member for

20 years 8 months

Make a copy of new project group (eg.PG01) and rename it (eg.PG02). The subproject will be copied together. Set PG01 as a baseline (target) schedule and PG02 as current working file. Go to Tools > Project Utilities > Targets and set PG01 as a target file for PG02.



Regards.

Member for

21 years

Hi john,



If you have the two target projects, combine them in the same way you did with the updated projects, in a multi project file, and add the same sub-project id’s, and use this group as your new target.

Member for

23 years

You would have to prefix the activity id’s in your target plan with the same prefix you used to create your sub-projects.



This can be done with a Global Change (Actid = xx&actid), though depending on how your activity id is made up you may need to use the ltrim or left/right text functions.





HTH