It is simple, create a resource code for each trade, and add the resources to the program, eg Resource CONC is concrete work, FINI is finishes etc. Then run s-curves for each resource, this will give you what you need.
You can do from Schedule itself ,Create column Planned % ( Baseline at datadate -Updated % ) Actual% (% completion ) in schedule Itself . Take Print out, If you dont want Bar chart ,Tick off the Option.
You can summarised this Schedule as report. I dont think any problem.
Member for
23 years
Member for23 years
Submitted by george stewart on Thu, 2005-03-17 04:01
If you set up a new export file, then filter your selection and use the target % complete and actual % complete. run this and you will get the results required.
See Tools, Project Utilities, Export. If you require more help come back
Member for
21 years 1 monthRE: Trade Filter
Thanks
Philip
your answer open the thought, but still if you would elaborate with example and how can open the code from the p3 etc will be more helpful
Regards
Azvi
Member for
21 yearsRE: Trade Filter
Hi Azvi,
It is simple, create a resource code for each trade, and add the resources to the program, eg Resource CONC is concrete work, FINI is finishes etc. Then run s-curves for each resource, this will give you what you need.
Regards
Member for
20 years 8 monthsRE: Trade Filter
Hi,
Why you want to export the activity.
You can do from Schedule itself ,Create column Planned % ( Baseline at datadate -Updated % ) Actual% (% completion ) in schedule Itself . Take Print out, If you dont want Bar chart ,Tick off the Option.
You can summarised this Schedule as report. I dont think any problem.
Member for
23 yearsRE: Trade Filter
If you set up a new export file, then filter your selection and use the target % complete and actual % complete. run this and you will get the results required.
See Tools, Project Utilities, Export. If you require more help come back
George
Member for
21 years 1 monthRE: Trade Filter
Hi
I intent to produce report for each trade progress
exp:
Planned% Actual% Slippage
Earth work ----- ----- ----
Concrete work ----- ------ ----
Finishing work ----- ------ ----
Thanks
Member for
21 years 3 monthsRE: Trade Filter
Could you eloborate your question? What exactly you want to do?