INDIVIDUAL PROGRESS

Member for

17 years 5 months

Dear Kumar,

SD = Shop Drawings

I wonder, if they ares sendeing the SD of cabines "one Cabine/one week" sure the first one or two SD activities may be Critical, but the others will not affect the critical path. and that depend on the duration assumed for one cabine.

Only if you upload a different team for each Cabin, i wonder what funny Man-hours histogram you will get.?



now you want to know the Planned progress at a specific date?

y dont you try the (CTRL+F9). but if the SD activities are not broken down and linked as reality, the CTRL+F9 will give you a false report. To fix that, you can tie by a constraint the driving (1st) activity of each Cabin Manufacturing. and suppose the programme with constraints as you new baseline, sure the ending dates will be affected.