Primavera Project Planner - P3 Member for 20 years 3 months Member for 20 years 3 months Submitted by Gordon Blair on Fri, 2006-01-13 10:11 Permalink RE: Budget quantity for milestones Umm have you tried just adding it into the cost window? Resource What ever you want to call it Budgeted Cost how much it is As long as youve got the relevant resource in the dictionary, doesnt appear to cause a problem. This is how I do all my Milestone payments. Let me know how you get on? Cheers Gordon Log in or register to post comments
Member for 20 years 3 months Member for 20 years 3 months Submitted by Gordon Blair on Fri, 2006-01-13 10:11 Permalink RE: Budget quantity for milestones Umm have you tried just adding it into the cost window? Resource What ever you want to call it Budgeted Cost how much it is As long as youve got the relevant resource in the dictionary, doesnt appear to cause a problem. This is how I do all my Milestone payments. Let me know how you get on? Cheers Gordon
Member for
20 years 3 monthsRE: Budget quantity for milestones
Umm have you tried just adding it into the cost window?
Resource What ever you want to call it
Budgeted Cost how much it is
As long as youve got the relevant resource in the dictionary, doesnt appear to cause a problem.
This is how I do all my Milestone payments.
Let me know how you get on?
Cheers
Gordon