BACK-UP AND RESTORE SCHEDULE

Member for

21 years 5 months

No, you do not have to crate a target project.

Most likely you had a target project together with the project you backed up. When you do the back up, I guess you only did a back up for the main project, and not for the target project. If you dont need the back up for the target project (and dont want to do a back up for it) then you can chose project overview/targets and delete the targetproject that P3 is looking for when you open the backed up project. Then you can open your plan.

yours/