Q1. Time duration cannot reduce. Only one excavator, complete the activities one by one. Duration of each activity will depends on the production rate.
Q2. If in resource library, stated the upper limit of excavator is 2, then do a schedule and level to the network, over duration may cut down since 2 activities are in progress "parallel"
Member for
23 years 8 monthsRE: Resource Requirement in P3
Q1. Time duration cannot reduce. Only one excavator, complete the activities one by one. Duration of each activity will depends on the production rate.
Q2. If in resource library, stated the upper limit of excavator is 2, then do a schedule and level to the network, over duration may cut down since 2 activities are in progress "parallel"